Home

 Remodeling Begins 

We're already wanting to finish the basement and have only lived here less than two years!  The original design planned on this remodeling so it shouldn't be too bad to complete which is good because I'm doing most of the work.  I plan on having a lot of help and advice from friends.



It all starts with a drawing.  We revised the original design of the finished basement from the original plan.  Items such as the bathroom stayed the same, though, because it would've been too expensive to relocate the rough plumbing. Once the drawing was finished I had to do an estimate.  I was careful on my quantities because I didn't want to have too much left over.  To save cost, I had a lot of my supplies delivered at once.   This made parking in the Garage difficult for a while (but not impossible).


I protected the existing carpet in the Family Room with this runner. The material is like a very heavy cardstock.


Getting some of storage areas cleared up and ready for the remodeling isn't going to be easy.


One of the first tasks was connecting the rough plumbing for the shower. since the exact shower stall wasn't specified during construction, the contractor blocked out an opening in the slab.   I had to figure out the location of the drain.  This is the underside of the fiberglass shower deck.

 


The blocking is removed in this shot.  I had to dig down to locate the capped vent.


This pipe connects to the existing sewer lines.  Notice the versatility of duct tape.


I had to dig down further to get the trap in place.  Then I determined the height of the drain.  Once I figured it all out, I cut the pieces of pipe and dry fitted the parts.  A friend helped me with this. since everything looked good, I marked a line on the pipes to realign them then took them apart to put the glue.


I carefully filled the hole with the gravel that I had removed. This part is done.


Due to code, my contractor couldn't leave the structure exposed in the unfinished portions of basement when the house was built. He placed insulation and vapor barrier on my wood stud walls and a plastic-backed insulation to cover the concrete walls. Before I began putting up metal studs I sealed some areas and secured loose spots. 


Beginning to lay up my studs. I chose to make the metal stud wall adjacent to the concrete wall straight instead of putting a ledge where the wall thicknesses were different. I used 20 gauge steel which is thicker than standard.  It was stiffer but harder to cut.  All in all it was a good choice.


I chose metal studs because they are straight and easy to work with as non-structural walls.  They go together much like an erector set.  A special channel is tap-conned into the concrete.  Then another is secured to the joists above.  The wall stud is then slipped into the channels, checked for level and secured in place while it is screwed at the top and bottom.  laying out stud spacing is important or headaches will occur when the gypsum board is installed.


 


 When the top channel is parallel with the joists, another channel is cut with tabs and secured between two joists as support.  If it is perpendicular, the top channel can just be secured to the joists.  

 


 We had to frame around existing ductwork.  This shot depicts the area just above the shower. I decided to drop down the ceiling in the shower so it wouldn't look too cut up.  I am also going to use this area as a soffit to run the vent.
 


 This is a capped vent for the future toilet. This vent was installed when the house was originally built.  When we opened up the vent to connect it to the new toilet vent, water gushed out.  The vent opens up through the roof and it had been collecting rainwater.  This picture also shows that the steel top channel had to be cut around the vent.

<Prev   ~   Back to Top   ~   Next>